MAJOR GOALS BY PHASE

PHASE 1  (North On-Site Area)
Demolition of the 210 fifty-year old public housing units is complete.
This phase is comprised of 83 rental units which are now complete and 100% occupied as well as the 15 for-sale homes. The construction of a new 23,000 square foot community center called Elgin Station is also complete.
 
HUD approval to proceed: December  2002
Demolition Completion: February 2003
Construction Start:    March 2003                 
Construction Finish: Completed October 2006 (Rental)    Construction Finish: Completed October 2004 (For Sale)
 
PHASE 2  (Lanvale On-Site Area)
New construction of 45 rental units.
HUD Approval to Proceed: January 2004
Construction Start:  February 2004
Construction Finish:  Completed March 2005 (Rental)
 
PHASE 3 (Lanvale Off-Site Area)
New construction of 77 rental and 2 Habitat for-sale homes.
HUD approval to proceed: October 2004
Construction start:  December 2004                                         Construction finish:  December 2005 (Rental)                           Construction Finish: December 2006 (For Sale - Off-site)
 
PHASE 4 (County Property/Westport Drive Off-Site Area)
New construction of 85 rental homes and 45 for sale homes.
HUD approval to proceed: July 2005
Construction start:  August 2005
Construction finish: December 2006
 
Neighborhood Beautification Program                                            Exterior rehab of 49 existing neighborhood homes.

Rehab start:  March 2005                                                                     Rehab Completion: September 1, 2005

 

HOPE VI PROGRAM GOALS

 
  • ECONOMIC SELF SUFFICIENCY
  • EMPLOYMENT
  • SAVINGS TOWARD HOMEOWNERSHIP
  • LIFE SKILLS AND TRAINING
  • COUNSELING AND SUPPORT
  • AFTER SCHOOL ACTIVITIES
  • ADULT BASED EDUCATION
  • CHILDCARE - HEALTH CARE
  • TRANSPORTATION
  • JOB TRAINING AND PLACEMENT
  • APPRENTICESHIP PROGRAMS
  • CASE MANAGEMENT
  • SECTION 3 MBE/WBE OPPORTUNITIES